Parsonage Houses - Repairs - Minor Works
1. Minor Works
- All works, other than those that are urgent (see 4
Emergency Work), are to be authorised by the Residential Property Department
before any work is instructed.
- All works costing £100 or under (including
VAT) should normally be met by the PCC, or by the occupier.
- For works over £100, but under £500
(excluding VAT), at least two estimates are required.
- For works over £500 (excluding VAT),
a minimum of three estimates are required.
Further guidance is given in the 'Minor Works Handbook' (including a list of
recommended contractors). Unless these procedures are followed, there is no
guarantee that expenditure of this nature will be met by the Diocese.